RISK ASSESSMENT ON INSTALL AND DISMANTLE SCAFFOLDING USING TASK RISK ASSESSMENT METHOD

 Abstract views: 349

Authors

  • Talitha Cornelia Azura Politeknik Perkapalan Negeri Surabaya
  • Moch. Luqman Ashari Politeknik Perkapalan Negeri Surabaya
  • Rina Sandora Politeknik Perkapalan Negeri Surabaya

DOI:

https://doi.org/10.36456/tibuana.2.02.1940.9-13

Keywords:

Install and Dismantle Scaffolding; Initial Risk; Residual Risk.

Abstract

Accidents can occur anytime and anywhere such as accidents that occur at work at height. This study aims to identify and analyze potential hazards in the install and dismantle scaffolding work using TRA (Task Risk Assessment) method. The results of the risk assessment using TRA on this work obtained four job description with 2 jobs at low risk, namely initial risk of 4 and after controlling for residual risk of 2. For install and dismantle scaffolding show that medium risk was obtained with an initial risk of 12 and after controlling, the residual risk becomes 9.

Downloads

Download data is not yet available.

References

Alvani, I. N. “Penilaian Risiko dan Perencanaan Kegiatan Perawatan Ketel Uap Menggunakan Metode RCM II dan Identifikasi Bahaya Menggunakan TRA di PT.Xâ€, Surabaya, (2016).

Department of Occupational Safety and Health Ministry of Human Resources, “Guidelines of Hazard Identification, Risk Assesment and Risk Controlâ€, Malaysia, (2008).

Febrianto, D., Muliatna, I. M., “Study Identifikasi Bahaya dan Penilaian Resiko dengan menggunakan Metode TRA ( Task Risk Assessment) di Unit Workshop Perawatan Mesin 1 sebagai Upaya Pencegahan Kecelakaan Kerja di PT. PJB UBJ O&M Tanjung Awar-Awarâ€.

“Operating Risk Assessmentâ€, unpublished.

Downloads

Published

2019-07-31

How to Cite

Azura, T. C., Ashari, M. L. ., & Sandora, R. . (2019). RISK ASSESSMENT ON INSTALL AND DISMANTLE SCAFFOLDING USING TASK RISK ASSESSMENT METHOD. Tibuana, 2(02), 9–13. https://doi.org/10.36456/tibuana.2.02.1940.9-13

Issue

Section

Article