Design and Build of Dacron Pillow Filling Machine to Increase Production Capacity and Reduce Production Costs

 Abstract views: 141

Authors

  • Carendy Indrawan Universitas 17 Agustus 1945 Surabaya
  • Hery Murnawan Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.36456/tibuana.7.2.8889.90-97

Keywords:

Anthropometry; Production capacity; Production cost

Abstract

This research was conducted at Mr. Khambali's SME. Mr. Khambali's pillow SME is engaged in producing pillows and bolsters with an average daily production of 140 units. The problemin Mr. Khambali's pillow SME is that the production output often does not meet demand because the process of stuffing the dacron into the pillow sack takes 8 minutes. This research aims to increase production capacity and reduce production costs. The method used in this research is Anthropometry, which is a reference for designing the machine to ensure its safe and comfortable use. Then, work time measurement is conducted using the time study method, and the calculation of production costs is compared before and after the design process. The results obtained from the design process are an increase in production from 140 units to 230 units per day and a reduction in production costs from IDR. 23,801 to IDR. 14,705. This research concludes that after designing the Dacron pillow-filling device, production increased by 90 units, and production costs decreased by IDR. 9,096.

Downloads

Download data is not yet available.

References

-1:2000, I. (2021). Ergonomic design for safety of machinery--Part 1:pronciples for determining the dimensions required for openings for whole-body access into machinery. International standard to be revised.

Arba, H. N. (2017). Identifikasi Logam Besi (Fe) Pada Zonasi Radius 1-5 KM Tempat Pembuangan Akhir (TPA) Antang Makassar Terhadap Pemgaruh Kualitas Air Sumur Galian. Makassar: FAKULTAS SAINS DAN TEKNOLOGI UNIVERSITAS ISLAM NEGERI ALAUDDIN MAKASSAR.

Arbiansyah, I. C., & Wati, P. E. (2023). Rancang Ulang Alat Mixer Adonan Mie Basah guna Meningkatkan Kapasitas dan Efisiensi Produksi pada Home Industry Mie Ilmi. TEKNIKA, 354 - 362.

Astuti, R. D., & iftadi, i. (2016). Analisis dan Perancangan sistem kerja. surakarta: Grup Penerbitan CV Budi Utama.

Bahri, S., Mariani, W. E., & Muslichah. (2021). Akutansi Biaya. Yogyakarta: ANDI.

Barnes, R. M. (1980). Motion and time study design and measurment of work. New York: John wiley & sons.

Cahyawati, A. N., Munawar, A. F., Anggraini, A., & Rizky, D. A. (2018). Analisis Pengukuran Kerja dengan menggunakan metode stopwatch time study.Seminar Nasional Teknologi dan Rekayasa (SENTRA) , 107.

Darama, S., hanifi, r., & reza. (2023). Rancang Bangun Mesin Pengisi Bantal Sebagai Alat Bantu Produktivitas. Jurnal Ilmiah Wahana Pendidikan, 603 - 609.

Ginting, R. (2009). Perancangan Produk. Medan: Graha Ilmu.

Hidayat, R. (2021). Pembuat Roda Mesin Penggembur Tanah. Tegal: Pembuat Roda Mesin Penggembur Tanah Pembuat Roda Mesin Penggembur Tanah.

huda, a. y. (2023). Rancang bangun mesin amplas meja guna untuk meningkatkan output produksi alas meja kuliah pada proses penghalusan . 50 -62.

Irawan, A. P. (2017). Perancangan dan Pengembangan Produk Manufaktur. Jakarta: ANDI.

Kusnawa, W. S. (2015). Antropometri Terapan untuk Perancangan Sistem Kerja. Bandung: PT Remaja Rosdakarya.

murnawan, h., & setiawan, o. r. (2023). Reengineering Produksi Pegangan Rantang Soto Guna Meningkatkan Produktivitas . TEKNIKA, 50 - 60.

Pujawan, I. N. (2019). Ekonomi Teknik Edisi 3. Surabaya: Lautan Pustaka.

SUYANTO, V. (2016). Analisa Performa Motor DC Feedback Tipe No. 63 – 110 Di Laboratarium Listrik Dan Otomasi Kapal. Surabaya: Jurusan Teknik Sistem Perkapalan Fakultas Teknologi Kelautan Institut Teknologi Sepuluh Nopember.

Taringan, M. (2015). Pengukuran Standart Waktu Kerja Untuk Menentukan Jumlah Tenaga Kerja Yang Optimal.Wahana Inovasi, 30.

Walpole, R. (1998). Pengantar Statistika. 1998: Gramedia.

Wati, P. D., & Murnawan, H. (2023). Pemanfaatan Oli Bekas Pada Perancangan Tumgku Peleburan Guna Memnimalkan Harga Pokok Produksi Aluminium Batangan. Tekmapro : Journal of Industrial Engineering and Management, 48 - 60. DOI: https://doi.org/10.33005/tekmapro.v18i1.289

Wati, P. E., & Miraningsih, Y. M. (2023). Perancangan Ulang Alat Guna Mengoptimalkan Kinerja Alat Pemintal Pada Proses Pemotongan Bahan Baku Tas Anyaman. KAIZEN: MANAGEMENT SYSTEMS & INDUSTRIAL ENGINEERING JOURNAL, 1 - 10.

wati, p. e., & murnawan, h. (2022). Perancangan Alat Pembuat Mesin Potong Singkong Dengan Mempertimbangkkan Aspek Ergonomi. JISI: JURNAL INTEGRASI SISTEM INDUSTRI, 61 - 67. DOI: https://doi.org/10.24853/jisi.9.1.59-69

Wati, P. E., Murnawan, H., Putri, V. A., & Yuliati, E. L. (2022). Peningkatan Kualitas dan Kapasitas Produksi dengan Penggunaan Mesin Spinner pada Proses Produksi Keripik Sagu Tempe. Seminar Nasional Pengabdian kepada masyarakat 2022, 359 - 365.

Yanto, & Ngaliman , B. (2017). Ergonomi dasar dasar studi waktu dan gerak untuk analisis dan perbaikan sistem kerja. jakarta: Andi.

Yassierli, Pratama, G. B., Pujiartati, D. A., & Yamin, P. A. (2020). Ergonomi Industri. Bandung: PT Remaja Rosdakarya.

Zaini, A., Wati, P. D., & Riyadi, S. (2023). ANALISIS KELAYAKAN INVESTASI ALAT ROLL STREAPING PADA UKM MEKAR HANDCRAFT.TEKNIKA, 136 - 146. DOI: https://doi.org/10.30996/agro.v2i01.9688

Downloads

Published

2024-07-28

How to Cite

Carendy Indrawan, & Murnawan, H. (2024). Design and Build of Dacron Pillow Filling Machine to Increase Production Capacity and Reduce Production Costs. Tibuana, 7(2), 90–97. https://doi.org/10.36456/tibuana.7.2.8889.90-97

Issue

Section

Article

Most read articles by the same author(s)