Implementation of Critical Chain Project Management Method on Controlling the Pipeline Project

 Abstract views: 33

Authors

  • Rina Sandora Politeknik Perkapalan Negeri Surabaya
  • Dini Rosyadah Tridya Politeknik Perkapalan Negeri Surabaya

DOI:

https://doi.org/10.36456/tibuana.8.1.9988.15-21

Keywords:

Critical Chain Project Management; Duration; Scheduling

Abstract

In the implementation of construction projects, the incompatibility between plan and actual schedule that cause an additional time and cost is oftenly occurring. The Pipeline Project started in July 2022 and scheduled for completion in November 2022. However, in actuality the project finished in July 2023. Based on this case, an acceleration method needs to be implemented so that the project can be completed quickly and efficiently. One of the methods applied is Critical Chain Project Management (CCPM). Scheduling is carried out using the actual duration of the project that applied with CCPM. The actual duration of the project is 318 days. Furthermore, by using the CCPM, the duration is become 216 days. So, by using the CCPM, the project is completed 32.08% faster than the actual duration of the project. Based on the results of the analysis, by applying the CCPM method is able to make an optimal duration of the project.

Downloads

Download data is not yet available.

References

Arvianto, Ramanda N., & Ryan. (2015). “Penerapan Critical Chain Project Management Untuk Keterbatasan Resources Di Pt Berkat Manunggal” 4 (2): 1-7.

Azis, S., Hargono, E., & Supriadi, D. (2017). Evaluasi Penjadwalan Pembangunan Hanggar PT. Gudang Garam, Tbk Menggunakan Metode Critical Chain Project Management (Studi Kasus Pembangunan Hanggar PT. Gudang Garam, Tbk Di Waru, Sidoarjo, Jawa Timur). Jurnal Info Manajemen Proyek Vol. 8.2 (pp. 30-42). Malang: Institut Teknologi Nasional.

Efendi, M. R., Arumsari, N., Rizal, M. C. (2020). Optimasi Penjadwalan Proyek North Acid Gas Flare RDMP RU-V Balikpapan Melalui Lintasan Kritis PDM dan Percepatan Crash Duration. Proceedings Conference on Piping Engineering and Its Application 5(1), 276-281. Surabaya.

Goldratt, E. M. (1997). Critical Chain. Great Barrington, Massachusetts: North River Press

Larasati, Dian Aprilia, & Sutopo, Wahyudi. (2020). “Analisis Efektivitas Jadwal Proyek Implementasi Software Dengan Critical Path Method: Studi Kasus ”. Jurnal INTECH Teknik Industri Universitas Serang Raya 6 (1), 55-64. DOI: https://doi.org/10.30656/intech.v6i1.2292

Lee, S., Kim, B. and Kim, H. (2012) An Integrated View of Knowledge Management for Performance. Journal of Knowledge Management, 16, 183-203. DOI: https://doi.org/10.1108/13673271211218807

Malau, A. Z. (2019). Aplikasi Metode Critical Chain Project Management dalam Pemansangan Dinding Proyek Area Mall Podomoro City Deli Medan. Medan: Fakultas Matematika dan Ilmu Pengetahuan Alam, Universitas Sumatera Utara.

Nasution, S. R. (2014). Penerapan Metode Critical Chain Project Management untuk Perencanaan Proyek Very Low Pressure Phase-II KEI Ltd. Universitas Pancasila. Jakarta: Jurnal Teknologi Technoscientia.

Newbold, R. C. (1998). Project Management in the Fast Lane: Applying the Theory of Constraints. St. Lucie Press. Florida, Amerika Serikat.

Ramadhan, A. R. (2021). Optimasi Penjadwalan Proyek Jaringan Gas Rumah Tangga Menggunakan Metode Project Crashing dan Least Cost Schedulings. Proceedings 6th Conference on Piping Engineering and Its Application. Surabaya.

Ramanda, R., & Arvianto, A. (2015). Penerapan Critical Chain Project Management untuk Mengatasi Masalah Multi Proyek dengan Keterbatasan Resources di PT Berkat Manunggal Jaya. Semarang: Universitas Diponegoro.

Rev, E. (2003). Work Breakdown Structure.

America: U.S. Department of Energy.

Santosa, B. (2009). Manajemen Proyek: Konsep dan Implementasi (First Edition). Yogyakarta: Graha Ilmu.

Schwalbe, K. (2004). Information Technology Project Management (Fourth Edition). Course Technology, Inc. Boston.

Siswanto, A. B., & Salim, M. A. (2015). Manajemen Proyek.

Soeharto, I. (1999). Manajemen Proyek (Dari Konseptual Sampai Operasional) Jilid 1 Edisi Kedua. Jakarta: Erlangga.

Subakir, A. H., & Sugiyanto. (2022). Analisis Duration Cost Trade Off Untuk Mengejar Keterlambatan Pelaksanaan Proyek (Studi Kasus: Peningkatan Jalan Simorejo - Baureno Kabupaten Bojonegoro Jawa Timur). Rang Teknik Journal, 5(1), 8-23. DOI: https://doi.org/10.31869/rtj.v5i1.2705

Sugiyanto. (2021). Manajemen Proyek Rantai Kritis. Surabaya: Cipta Media Nusantara.

Suherman, & Aulia, A. (2016). Pengendalian Waktu Proyek dengan Menggunakan Metode Critical Chain Project Management (CCPM) (Studi Kasus: Pembangunan Jalan SMK IT Payakumbuh). Jurnal Teknik Industri Vol. 2 No. 2, (pp. 103-111). Pekanbaru. DOI: https://doi.org/10.24014/jti.v2i2.5093

Wardana, R. A. (2020). Studi Analisa Biaya dan Waktu pada Perencanaan Pembangunan Gudang Umum RSUD Sidoarjo menggunakan Metode Critical Chain Project Management. Surabaya: Universitas 17Agutus 1945.

Downloads

Published

2025-01-14

How to Cite

Sandora, R., & Tridya, D. R. . (2025). Implementation of Critical Chain Project Management Method on Controlling the Pipeline Project. Tibuana, 8(1), 15–21. https://doi.org/10.36456/tibuana.8.1.9988.15-21

Issue

Section

Article